... North American Pipeline Project Roundup: November/December 2020 - North American Energy Pipelines
 

North American Pipeline Project Roundup: November/December 2020

Environmental Reclamation Solutions (ENREC) was awarded a contract by Precision Pipeline LLC for the concrete coating of approximately 18,000 ft of 36-in. pipe in Carlton Counties, Minnesota. Headquarters is Grand Rapids, Minnesota. The superintendent is Randy Rubenzer. Estimated start date: Oct. 26.

Intercon Construction Inc. was awarded a contract by Northern Natural Gas to install approximately 3,500 ft of 2-in. pipeline via horizontal directional drilling in Webster County, Iowa. Headquarters is Fort Dodge, Iowa. The superintendent is Carl Bubolz. Estimated start date: Oct. 26.

R.L. Coolsaet Construction Co. was awarded a contract by DTE Energy for four anomaly replacement digs on a 24-in. pipeline in Shiawassee County, Michigan. Headquarters is Owosso, Michigan. The superintendent is Kevin Scully. Estimated start date: Oct. 26.

/*** Advertisement ***/

Henkels & McCoy Inc. was awarded a contract by Spectra Energy Transmission II (Enbridge) to recoat an undetermined length of pipeline in Boyle County, Kentucky. Headquarters is Junction City, Kentucky. The superintendent is Dave Csepegi. Estimated start date: Oct. 19.

Northern Clearing Inc. was awarded a contract by Precision Pipeline LLC for the clearing of approximately 7 miles of 42-in. pipeline right-of-way in Roanoke and Franklin Counties, Virginia. Headquarters is to be determined. The superintendent is Duanne Kmieciak. Estimated start date: Oct. 19.

Snelson Cos. Inc. was awarded a contract by Xcel Energy the take up of approximately 5,200 ft of 2-in. pipeline and the re-lay of approximately 5,200 ft of 3- and 4-in. pipeline in Routt County, Colorado. Headquarters is Steamboat Springs, Colorado. The superintendent is Kevin Hartsell. Estimated start date: Oct. 19.

T.G. Mercer Consulting Services Inc. was awarded a contract by Texas Gas Transmission for the offloading and racking of approximately 10,960 ft of 20-in. pipe and yard contraction in Sullivan County, Indiana. Headquarters is Willow Park, Texas. The superintendent is Larry Rodriguez. Estimated start date: Oct. 19.

B&N Clearing and Environmental LLC was awarded a contract by Price Gregory International Inc. for the clearing and matting of approximately 2 miles of 42-in. pipeline right-of-way in Greenbrier, Summers and Monroe Counties, West Virginia. Headquarters is Mount Hope, West Virginia. The superintendent is Kevin Newcomb. Estimated start date: Oct. 14.

Minnesota Limited LLC was awarded a contract by Vectren to fabricate, test and install 80 ft of 3- and 4-in. pipeline in Posey County, Indiana. Headquarters is Mt. Vernon, Indiana. The superintendent is Doug Vaughn. Estimated start date: Oct. 12.

Aaron Enterprises Inc. was awarded a contract by Washington Gas/Infrasource LLC to install approximately 180 ft of 20-in. pipeline via jack and bore in Frederick County, Virginia. Headquarters is Winchester, Virginia. The superintendent is Glenn Grove. Estimated start date: Oct. 7.

InterCon Construction Inc. was awarded a contract by Northern Natural Gas for the replacement of an undetermined length of 40- and 16-in. pipeline in Houston County, Minnesota. Headquarters is Hokah, Minnesota. The superintendent is Carl Bubolz. Estimated start date: Oct. 1.

Pe Ben USA Inc. was awarded a contract by American Cast Iron Pipe Co. for the transportation, offloading and yard contraction for approximately 55.27 miles of 16-in. pipe in Jefferson, Choctaw and Washington Counties, Alabama. Headquarters are Birmingham, Leroy and Silas, Alabama. The superintendent is Tim Gray. Estimated start date: Oct. 1.

Pe Ben USA Inc. was awarded a contract by TC Energy for pipeline yard construction and maintenance in McCome, Fallon, Dawson and Valley Counties of Montana and Mead County, South Dakota. Headquarters is to be determined. The superintendent is Donnie Gagert. Estimated start date: Oct. 1.

United Piping Inc. was awarded a contract by Consumers Energy to install approximately 1,120 ft of 10-in. pipeline and 450 ft of 8-in. pipeline, and accompanying valves in Washtenaw and St. Clair Counties, Michigan. Headquarters is Northville, Michigan. The superintendent is Mike Manley. Estimated start date: Sept. 30.

InterCon Construction Inc. was awarded a contract by Buckeye Partners for the replacement of approximately 1,200 ft of 14-in. pipeline in Madison County, Illinois, and the replacement of approximately 1,000 ft of 12-in. pipeline in Fayette County, Illinois. Headquarters is Vandalia, Illinois. The superintendent is Carl Bubolz. Estimated start date: Sept. 29.

Dun Transportation and Stringing Inc. was awarded a contract by Kinder Morgan to load and haul to the pipeline right-of-way approximately 7 miles of 42-in. pipe in Kimble, Gillespie, and Blanco Counties, Texas. Headquarters is the pipe yard. The superintendent is Mike Bruce. Estimated start date: Sept. 28.

Minnesota Limited LLC was awarded a contract by TC Energy for earthwork modification around an existing pig barrel in Gibson County, Tennessee. Headquarters is Bradford, Tennessee. The superintendent is Chris Jones. Estimated start date: Sept. 28.

Intercon Construction Inc. was awarded a contract by Northern Natural Gas for TBS station removal consisting of 4” to 8” piping in Nobles County, Minnesota. Headquarters is Worthington Minnesota. The superintendent is Carl Bubolz. Estimated start date: Sept. 23.

United Piping Inc. was awarded a contract by Blue Water Gas to lift and support approximately 1,380 ft of 20-in. pipeline for painting in St. Clair County, Michigan. Headquarters is Marysville, Michigan. The superintendent is Joel Bailer. Estimated start date: Sept. 21.

U.S. Pipeline Inc. was awarded a contract by TC Energy (Columbia Gas Transmission) work associated with the abandonment of approximately 16.8 miles of 20-in. pipeline in Jackson, Gallia and Lawrence Counties, Ohio. Headquarters is Jackson, Ohio. The superintendent is Cliff Sinclair. Estimated start date: Sept. 21.

Intercon Construction Inc. was awarded a contract by Jimmy Dunn Excavating/WV American Water to install approximately 1,800 ft of 12-in. pipeline in West Virginia. Headquarters is Shrewsbury/East Bank West Virginia. The superintendent is John Olson. Estimated start date: Sept. 16.

Aaron Enterprises Inc. was awarded a contract by The Hillis Group LLC for installation of approximately 300 ft of 30-in. pipeline via jack and bore in Baltimore County, Maryland. Headquarters is Owning Mills, Maryland. The superintendent is Glenn Grove. Estimated start date: Sept. 14.

United Piping Inc. was awarded a contract by Enbridge for three 24-in. pipeline integrity digs in Ingham County, Michigan. Headquarters is Dansville, Michigan. The superintendent is Kendal Pilarski. Estimated start date: Sept. 14.

T.G. Mercer Consulting Services Inc. was awarded a contract by Strike for yard preparation and the offloading and racking of approximately 65,000 ft of 24-in. pipe in Jefferson County, Texas. Headquarters is Willow Park, Texas. The superintendent is Mario Montgomery. Estimated start date: Sept. 8.

Tags: ,

Comments are closed here.