... North American Pipeline Project Roundup - North American Energy Pipelines
 

North American Pipeline Project Roundup

The following oil and gas pipeline projects have been announced. Projects are in order of most recent approximate starting date. All projects are for 2013 unless noted.

Northern Clearing Inc. was awarded a contract by Michels Corp. for the clearing of approximately 144 miles of 36-in. pipeline right of way in Livingston, Woodford, Tazewell, Mason, Fulton, Schuyler, Brown and Adams counties, Ill. Headquarters is unknown. The superintendent is Daniel Vernon. Approximate start date: Aug. 8.

Northern Clearing Inc. was awarded a contract by U.S. Pipeline Inc. for the clearing of approximately 153 miles of 36-in. pipeline right of way in Allen, Wilson, Montgomery and Chautauqua counties, Kan., and Washington, Osage, Pawnee, Payne and Lincoln counties, Okla. Headquarters is unknown. The superintendent is Rod Grubisic. Approximate start date: Aug. 7.

Northern Clearing Inc. was awarded a contract by U.S. Pipeline Inc. for the clearing of approximately 149 miles of 36-in. pipeline right of way in Saline, Lafayette, Johnson, Cass and Bates counties, Mo., and Linn and Allen counties, Kan. Headquarters is unknown. The superintendent is Jim Junker Jr. Approximate start date: Aug. 7.

InfraSource LLC was awarded a contract by Enterprise Products for integrity digs, including welding of sleeves, on various size pipelines in Clearfield, Elk, Cameron and Potter counties, Pa. Headquarters is Cambridge, Ohio. The superintendent is Kirby Niebaum. Approximate start date: Aug. 5.

Utility Services Authority LLC was awarded a contract by C.J. Hughes Pipeline for the installation of approximately 2,200 ft of 10-in. pipeline via directional drilling in Pike County, Ky. Headquarters is Gulnare, Ky. The superintendent is Casey Sarkozi. Approximate start date: Aug. 5.

/*** Advertisement ***/

Midwest Underground Inc. was awarded a contract by Northern Natural Gas for the installation of approximately 10 miles of 2-in. pipeline in Butler, Seward and Gage counties, Neb. Headquarters is unknown. The superintendent is Shaun Tippie. Approximate start date: Aug. 1.

Price Gregory International Inc. was awarded a contract by Enterprise Products for the installation of approximately 97 miles of 16-in. pipeline and 19.2 miles of 20-in. pipeline in Sandoval, Bernalillo, Santa Fe, Torrance, Guadalupe, Lincoln, De Baca, Chaves and Lea counties, N.M. Headquarters is unknown. The superintendent is Mike Phillips. Approximate start date: Aug. 1.

Pipeline Energy Group Inc. (d/b/a Carl Smith Pipeline) was awarded a contract by Mark West for various 6-in. pipeline station work in Wetzel County, W.Va. Headquarters is West Union, W.Va. The superintendent is Eddie Smith. Approximate start date: August 2013 (announced July 22).

Minnesota Ltd. LLC was awarded a contract by Columbia Pipeline Group for the installation of a temporary separator with associated piping and the cleaning of 26- and 36-in. pipelines in Kanawha, Clay, Braxton, Upshur, Randolph, Pendleton and Hardy counties, W.Va. Headquarters is Clendenin, W.Va. The superintendent is Tim Dunn. Approximate start date: July 30.

Foltz Welding Ltd. was awarded a contract by Marathon Pipeline for the nitrogen purge of approximately 400 miles of 26-in. pipeline from Beaumont, Texas, to Longville, La., and the installation of approximately 400 ft of 4- and 6-in. pipelines in Longville, La., and Tutwiler and Fisherville, Miss. Headquarters is unknown. The superintendent is Rich Torrence. Approximate start date: July 29.

Laney Directional Drilling Co. was awarded a contract by ExxonMobil Pipeline Co. for the installation of approximately 1,061 ft of 8-in. pipeline in Brazoria County, Texas. Headquarters is on the jobsite. The superintendent is Jerry Cordova. Approximate start date: July 29.

Laney Directional Drilling Co. was awarded a contract by Sheehan Pipe Line Construction Co. for the installation of approximately 1,644 ft of 42-in. pipeline via directional drilling in Jackson Parish, La. Headquarters is on the jobsite. The superintendent is Jimmy Johnson. Approximate start date: July 29.

Appalachian Pipeline Contractors LLP was awarded a contract by Williams Northwest Pipeline Group to take up approximately 18,500 ft of 10-in. pipeline and lay approximately 18,500 ft of new 16-in. natural gas pipeline in King County, Wash. Headquarters is unknown. The superintendent is Bobby Rose. Approximate start date: July 25.

Pete Gould & Sons Inc. was awarded a contract by Dominion Peoples/Mascaro to install 6.5 miles of 20-in. steel pipeline in Johnstown, Pa. Approximate start date: July 25.

CBC Pipeline LLC was awarded a contract by Mark West Energy for the installation of approximately 9.52 miles of various lengths of 2- to 20-in. pipelines in Harrison County, Ohio. Headquarters is Cadiz, Ohio. The superintendent is Mark Elliott. Approximate start date: July 24.

Dun Transportation & Stringing Inc. was awarded a contract by Welspun/TransCanada to offload and stockpile approximately 50 miles of 36-in. pipe in Liberty County, Texas. Headquarters is the pipe yard. The superintendent is John Denton. Approximate start date: July 24.

Price Gregory International Inc. was awarded a contract by Dominion Transmission Inc. for rehabilitation work on approximately 17.36 miles of 6- to 30-in. pipelines in Armstrong, Beaver, Butler, Ind., and Westmoreland counties, Pa. Headquarters is Darlington, Pa. The superintendent is Doug Gregory. Approximate start date: July 24.

Precision Pipeline LLC was awarded a contract by Access Midstream for the installation of approximately 23 miles of 6-, 8-, 10- and 12-in. pipeline in Greene County, Pa. Headquarters is Triadelphia, W.Va. The superintendent is Mark Wright. Approximate start date: July 22.

Utility Services Authority LLC was awarded a contract by R.L. Coolsaet Construction Co. for the installation of approximately 3,800 ft of 12-in. pipeline via directional drilling at eight locations in Franklin County, Ohio. Headquarters is unknown. The superintendent is Casey Sarkozi. Approximate start date: July 22.

Dun Transportation & Stringing Inc. was awarded a contract by Enterprise to unload and stockpile approximately 20 miles of 16-in. pipe m Cook County, Ill. Headquarters is the pipe yard. The superintendent is Johnny Denton. Approximate start date: July 19.

Pedero Pipe Support Systems USA was awarded a contract by Michels Corp. to spray foam breakers on 4 miles of 30-in. pipeline in Potter County, Pa. Headquarters is Coudersport, Pa. The superintendent is Kirk Baker. Approximate start date: July 16.

InfraSource Construction LLC was awarded a contract by Enbridge for various pipeline integrity digs throughout southern Wisconsin. Headquarters is Portage, Wis. The superintendent is Chris Powell. Approximate start date: July 15.

Midwest Underground Inc. was awarded a contract by Kinder Morgan for the hydrotesting of 1 mile of 16-in. pipeline in Bureau County, Ill. Headquarters is unknown. The superintendent is Jeff Thomason. Approximate start date: July 15.

Pe Ben USA Inc. was awarded a contract by TransCanada Pipeline Co. to build a storage yard for 48 miles of 36-in. pipe in Chambers County, Texas. Headquarters is Rushville, Ill. The superintendent is Robert Doven. Approximate start date: July 15.

Sheehan Pipe Line Construction Co. was awarded a contract by CenterPoint Energy for the installation of 1,750 ft of 42-in. pipeline via directional drilling in Jackson Parish, La. Headquarters is Hodge, La. The superintendent is Thelbert Barnes. Approximate start date: July 15.

Snelson Cos. Inc. was awarded a contract by Enterprise Products Partners LP for the installation of 49.6 miles of 16-in. pipeline in Utah and 45.9 miles of 16-in. pipeline in Colorado in two spreads: Spread 1 is 78 miles in Garfield and Mesa counties, Colo., and Grand County, Utah; Spread 2 is 17.5 miles in Uintah County, Utah, and Rio Blanco County, Colo. Headquarters for Spread 1 is Fruita, Colo. Headquarters for Spread 2 is Rangely, Colo. The superintendent for Spread 1 is Keith Maxwell. The superintendent for Spread 2 is Don Cupit. Approximate start date: July 15 (for both spreads).

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric for the installation of 3.5 miles of 24-in. pipeline in Fresno County, Calif. Headquarters is unknown. The superintendent is Mark Zogg. Approximate start date: July 15.

Supreme Industries was awarded a contract by Price Gregory International Inc. for the clearing of 14.5 miles of 6-, 8- and 16-in. pipeline rights of way in Sullivan County, Pa. Headquarters is Dushore, Pa. The superintendent is Scott Thibodeau. Approximate start date: July 15.

U.S. Pipeline Inc. was awarded a contract by Dominion Transmission for the installation of approximately 9,200 ft of 24-in. pipeline and removal of a retired 24-in. pipeline in Prince William County, Va. Headquarters is Bristow, Va. The superintendent is Tommy Dunn. Approximate start date: July 15.
CBC Pipeline LLC was awarded a contract by Mark West Energy for the installation of 4.3 miles of 20-in. pipeline and 1 mile of 20-in. pipeline in Guernsey and Harrison counties, Ohio. Headquarters is Cadiz, Ohio. The superintendent is Mark Elliott. Approximate start date: July 11.

Henkels & McCoy Inc. was awarded a contract by Columbia Gas for the installation of approximately 4 miles of 8-in. pipeline in York County, Pa. Headquarters is Hanover, Pa. The superintendent is Ed Murphy. Approximate start date: July 10.

InterCon Construction Inc. was awarded a contract by Integrity Pipeline for the installation of 20- and 22-in. pipeline via directional drilling in Ritchie, Pleasants and Tyler counties, W.Va. Headquarters is unknown. The superintendent is Joe Schmeizer. Approximate start date: July 10.

Laney Directional Drilling Co. was awarded a contract by ExxonMobil Pipeline Co. for the installation of 1,123 ft of 8-in. pipeline via directional drilling in Colorado County, Texas. Headquarters is on the jobsite. The superintendent is Jerry Cordova. Approximate start date: July 10.

Foltz Welding Ltd. (d/b/a Continental Pipeline Services) was awarded a contract by Panhandle Eastern Pipe Line Co. for the abandonment of approximately 2 miles of 12-in. pipeline in Texas County, Okla. Headquarters is unknown. The superintendent is Joe Pennington. Approximate start date: July 9.

BigInch Fabricators and Construction Inc. was awarded a contract by Panhandle Eastern/Trunkline Gas Co. for the take up and re-lay of approximately 600 ft of 24-in. pipeline in Parke County, Ind., and the relocation of 600 ft of 30- and 26-in. pipeline in Elkhart County, Ind. Headquarters are Goshen and Rockville, Ind. The superintendent is Jim Shepler. Approximate start date: July 8.

Foltz Welding Ltd. (d/b/a Continental Pipeline Services) was awarded a contract by Oneok for the installation of approximately 200 ft of 20-in. pipeline via directional drilling in Oklahoma County, Okla. Headquarters is unknown. The superintendent is Gary Kliebolker. Approximate start date: July 8.

Foltz Welding Ltd. (d/b/a Continental Pipeline Services) was awarded a contract by Koch for the relocation and installation of approximately 100 ft of 8-in. pipeline in Madison, Ill. Headquarters is unknown. The superintendent is William Grimes. Approximate start date: July 8.

Laney Directional Drilling Co. was awarded a contract by Plains All American Pipeline for the installation of approximately 2,576 ft of 12-in. pipeline via directional drilling in St. Mary Parish, La. Headquarters is on the jobsite. The superintendent is Oscar Myers. Approximate start date: July 8.

Pipeline Energy Group Inc. (d/b/a Carl Smith Pipeline) was awarded a contract by Mark West Liberty for the installation of approximately 8.2 miles of 20-in. pipeline in Guernsey and Harrison counties, Ohio. Headquarters is Cambridge, Ohio. The superintendent is Donald “Bub” Smith. Approximate start date: July 8.

Utility Services Authority LLC was awarded a contract by Associated Pipe Line Contractors Inc. for the installation of approximately 5,180 ft of 20-in. pipeline via horizontal directional drilling at three locations in Mahoning and Columbiana counties, Ohio. Headquarters are on the jobsites. The superintendent is Ervin Yoder. Approximate start date: July 8.

BigInch Fabricators and Construction Inc. was awarded a contract by Panhandle Eastern for the installation of approximately 1,700 ft of 6-in. pipeline via directional drilling, the hydrostatic testing of approximately 10.1 miles of 6-in. pipeline, and the re-lay of 650 ft of 6-in. pipeline in Fulton, County, Ill. Headquarters is Canton, Ill. The superintendent is Frank Ayers. Approximate start date: July 1.

Right-of-Way Clearing and Maintenance Inc. was awarded a contract by Precision Pipeline LLC for the clearing of approximately 8.99 miles of 6- to 16-in. pipeline rights of way in Sullivan County, Pa. Headquarters is unknown. The superintendent is James Merenda. Approximate start date: early July 2013 (announced July 1).

Snelson Companies Inc. was awarded a contract by Pacific Gas & Electric for the hydrostatic testing of approximately 6.5 miles of 12-in. pipeline in Kern County, Calif. Headquarters is unknown. The superintendent is Marv LaRue. Approximate start date: July 1.

Snelson Companies Inc. was awarded a contract by Pacific Gas & Electric for the installation of approximately 10 miles of 12-in. pipeline in Stanislaus County, Calif. Headquarters is unknown. The superintendent is Lou McMullen. Approximate start date: July 1.

U.S. Pipeline Inc. was awarded a contract by Enbridge for the installation of approximately 150 miles of 36-in. pipeline in Linn, Bourbon, Allen, Neosho, Wilson, Montgomery and Chautauqua counties, Kan., and Washington and Osage counties, Okla. Headquarters is Independence, Kan. The superintendent is Jim Jennings. Approximate start date: unknown (announced July 1).

U.S. Pipeline Inc. was awarded a contract by Enbridge for the installation of approximately 150 miles of 36-in. pipeline in Saline, Lafayette, Johnson, Cass and Bates counties, Mo.; Linn County, Kan.; and Osage, Pawnee, Payne and Lincoln counties, Okla. Headquarters are Warrensburg, Mo., and Sand Springs, Okla. The superintendent is Thad Hutchens. Approximate start date: unknown (announced July 1).