Price Gregory International Inc. was awarded a contract by Enbridge Energy LP to install approximately 79.7 miles of 36-in. pipeline in Cook, Grundy, Kankakee, Livingston and Will counties, Illinois, and Lake County, Indiana. Headquarters is Kankakee, Illinois. The superintendent is Terry
McDaniel. Approximate start date: TBD (announced March 16).

Price Gregory International Inc. was awarded a contract by Columbia Gas Transmission/NiSource to install approximately 9.5 miles of 26-in. pipeline including three horizontal directional drills and piping modifications in Chester County, Pennsylvania. Headquarters is Downingtown, Pennsylvania. The superintendent is Buck Hines. Approximate start date: TBD (announced March 16).

Snelson Cos. Inc. was awarded a contract by TransCanada/ANR for a meter station, interconnect and main line valves in Shelby County, Indiana. Headquarters is on the jobsite. The superintendent is Wayne Long. Approximate start date: March 16.

/*** Advertisement ***/

Pipeline Energy Group (d/b/a Carl Smith Pipeline) was awarded a contract by MarkWest Utica EMG LLC to install approximately 2.5 miles of 12-in. pipeline in Belmont and Monroe counties, Ohio. Headquarters is Barnesville, Ohio. The superintendent is Donald Smith. Approximate start date: March 14.

InterCon Construction Inc. was awarded a contract by Minnesota Limited LLC to install approximately 1,200 ft of 8-in. pipeline via directional drilling in Belmont County, Ohio. Headquarters is on the jobsite. The superintendent is Joe Schmelzer. Approximate start date: March 11.

Price Gregory International Inc. was awarded a contract by NFG Midstream Clemont LLC to install approximately 1.82 miles of 30-in. pipeline in McKean County, Pennsylvania. Headquarters is Port Allegany, Pennsylvania. The superintendent is Todd Burleson. Approximate start date: March 10.

Michels Corp. was awarded a contract by TransCanada for the clearing of approximately 3 miles of 20-in. pipeline right of way in Morrow County, Oregon. Headquarters is Boardman, Oregon. The superintendent is Mark Zogg. Approximate start date: March 9.

Minnesota Ltd. LLC was awarded a contract by Rice Energy to install approximately 1,200 ft of 8-in. pipeline via horizontal directional drilling in Belmont County, Ohio. Headquarters is Belmont, Ohio. The superintendent is Tim Dunn. Approximate start date: March 9.

Pe Ben USA Inc. was awarded a contract by Spectra Energy for the hauling, unloading and stockpiling of approximately 16 miles of 42-, 36-, 16- and 12-in. pipe sections in New Haven and Windham counties, Connecticut. Headquarters is Cheshire, Connecticut. The superintendent is Robert Cooley. Approximate start date: March 9.

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric for 15 span digs and approximately 1,000 ft of recoating on 34-in. pipeline in San Bernardino County, California. Headquarters is on the jobsite. The superintendent is Adam Davison. Approximate start date: March 9.

Snelson Cos. Inc. was awarded a contract by Southern California Gas Co. for the replacement of approximately 2.5 miles of 10-in. pipeline in Kings County, California. Headquarters is on the jobsite. The superintendent is Cory VanderVoorden. Approximate start date: March 9.

Supreme Industries was awarded a contract by Price Gregory International Inc. for the clearing, grubbing and matting of approximately 9.5 miles of 26-in. pipeline right of way in Chester County, Pennsylvania. Headquarters is Downingtown, Pennsylvania. The superintendent is Claude R. St. Pierre. Approximate start date: March 9.

Right-of-Way Clearing and Maintenance Inc. was awarded a contract by Michels Corp./Dominion for the clearing approximately 11.78 miles of 36-in. pipeline right of way in Harris and Tuscarawas counties, Ohio. Headquarters is to be determined. The superintendent is James Merenda. Approximate start date: March 9.

Brandenburg Drainage Inc. was awarded a contract by Price Gregory International Inc. for the clearing of approximately 79.7 miles of 36-in. pipeline right of way in Cook, Grundy, Kankakee, Livingston and Will counties, Illinois and Lake County, Indiana. Headquarters is on the jobsite. The superintendent is Walt Brandenburg. Approximate start date: March 3.

Foltz Welding Ltd. (d/b/a Continental Pipeline Services) was awarded a contract by Shell Pipeline for the fabrication and installation of 12-in. station piping in Cook and Marion counties, Illinois. Headquarters is Des Plaines, Illinois. The superintendent is Kevin Cain. Approximate start date: March 3.

Henkels & McCoy Inc. was awarded a contract by Columbia Pipeline Group for the Millennium Pipeline pig runs in Delaware, Orange and Steuben counties, New York. Headquarters is on the jobsite. The superintendent is Bill Adams. Approximate start date: March 2.

Minnesota Ltd. LLC was awarded a contract by Columbia Gas Transmission to install approximately 8,000 ft of 16-in. pipeline including launcher/receiver in Greene County, Pennsylvania. Headquarters is on the jobsite. The superintendent is Gary Hawk. Approximate start date: March 2.

Snelson Cos. Inc. was awarded a contract by Pacific Gas & Electric for the remaining installation of approximately 2miles of 16-in. pipeline and tie-ins in Sacramento County, California. Headquarters is Isleton, California. The superintendent is Tony Glenn. Approximate start date: March 2.

Supreme Industries was awarded a contract by Sheehan Pipe Line Construction Co. for the clearing, grubbing and matting of approximately 16 miles of 42-in. pipeline right of way in Luzerne and Monroe counties, Pennsylvania. Headquarters is Mountain Top, Pennsylvania. The superintendent is Claude R. St. Pierre. Approximate start date: March 2.

T.G. Mercer was awarded a contract by Regency for the unloading and stockpiling of approximately 12.58 miles of 36-in. pipe in Brooke County, West Virginia. Headquarters is on the jobsite. The superintendent is Bruce Munro. Approximate start date: March 2.

Associated Pipe Line Contractors Inc. was awarded a contract by Columbia Gas Transmission LLC to install approximately 9.6 miles of 20-in. pipeline in Gloucester County, New Jersey. Headquarters is Swedesboro, New Jersey. The superintendent is Mark Nail. Approximate start date: Feb. 26.

Northern Clearing Inc. was awarded a contract by Sheehan Pipe Line Construction Co. for the hand cutting on approximately 14 miles of 30-in. pipeline right of way in Harris and Jefferson counties, Ohio. Headquarters is on the jobsites. The superintendent is Jim Junker Sr. Approximate start date: Feb. 25.

Dun Transportation & Stringing Inc. was awarded a contract by Evraz/Enbridge for the offloading and stockpiling of approximately 72 miles of 24-in. pipe in Polk County, Minnesota. Headquarters is Crookston, Minnesota. The superintendent is Greg Norman. Approximate start date: Feb. 23.

Minnesota Ltd. LLC was awarded a contract by Columbia Gas Transmission to install approximately 1,200 ft of 12-in. pipeline including one regulator/metering set in Washington County, Pennsylvania. Headquarters is Monongahela Township, Pennsylvania. The superintendent is Gary Hawk. Approximate start date: Feb. 23.

Supreme Industries was awarded a contract by Precision Pipeline LLC for the row tree felling to support the installation of approximately 5 miles of 24-in. pipeline in Bradford and Sullivan counties, Pennsylvania. Headquarters is on the jobsite. The superintendent is Claude R. St. Pierre. Approximate start date: Feb. 23.

Supreme Industries was awarded a contract by Precision Pipeline LLC for the clearing, grubbing and matting of approximately 12 miles of 16-, 12- and 8-in. pipeline right of way in Bradford and Wyoming counties, Pennsylvania. Headquarters is Wysox, Pennsylvania. The superintendent is Matthew Opel. Approximate start date: Feb. 23.

Phillips & Jordan Inc. was awarded a contract by Rockford Corp. for the clearing and grubbing of approximately 3.36 miles of 26- and 12-in. pipeline right of way in Susquehanna County, Pennsylvania. Headquarters is Montrose, Pennsylvania. The superintendent is Mark Smith. Approximate start date: Feb. 20.

Pe Ben USA Inc. was awarded a contract by Evraz to offload and stockpile approximately 74 miles of 16-in. pipe in McKenzie, Mountrail and Ward counties, North Dakota. Headquarters is on the jobsites. The superintendent is David Wright. Approximate start date: Feb. 23.

Snelson Cos. Inc. was awarded a contract by Enstar Natural Gas Co. for the construction of approximately 4.1 miles of 16-in. pipeline including two horizontal directional drills and approximately 1,000 ft of 20-in. pipeline via horizontal directional drilling near Kenai, Alaska. Headquarters is Kenai, Alaska. The superintendent is Keith Maxwell. Approximate start date: Feb. 23.

Northern Clearing Inc. was awarded a contract by Sheehan Pipe Line Construction Co. for the clearing of approximately 50 miles of 36-in. pipeline right of way in Belmont, Jefferson and Monroe counties, Ohio. Headquarters is on the jobsites. The superintendent is Rod Grubisic. Approximate start date: Feb. 17.